5,000 tons of steel, 80,000 sqm of PVC membrane roof

CompletedDesign & Build
Arctic Factory

Project definition

Structural works and detailed design, plus execution of roof and facade works: 5,000 tons of steel structure erection, 80,000 sqm of PVC membrane with detail design, 20,000 sqm of sandwich panel works and 5 km of exterior fence.

  • 5,000 tons of steel structure
  • 80,000 sqm PVC membrane
  • 20,000 sqm sandwich panels
  • 5 km exterior fence
Client
Arctic
Location
Dâmbovița
Sector
Industrial
Area
80,000 m²
Duration
18 months
CRAFT scope
Detailed execution design and build
Status
Completed